 
         
                in natural gas drilling and production in the Gulf of Thailand
 
                         
                        The success confirmed to Onshore Compression Station #2 in 2001
Rental Fleet with option to purchase
 
                         
             
                 
                         
                         
                        To boost the gas of Thailand, in the 4th transmission pipeline.
 
             
                 
                        Onshore Gas Compressor/ PTT OCS#1
EGAT South Bangkok Power Plant Reciprocating Gas Booster compressors : 1800 HP
 
                         
                         
                        Problem : Gas Compressor Lock up 
                                Solution :  Corrective Maintenance by
                                coordinating with Dresser Rand Malaysia , USA and Local workshop in Thailand
                                Completed : Within 22 days ahead of the schedule
                            
 
                         
                         
                         
                        This new Gas Turbine model is designed to increase gas transmission force stability and a longer run length from 20,000 hours to 50,000 hours—the exchange is at the Gas Compression Station, Kanchanaburi.
 
             
         
         
         
         
         
         
         
         
         
        